Single-Ply System

A single-ply system is the perfect solution for virtually horizontal low-slope roofs that require waterproofing superior to that of traditional asphalt shingles.

 

 

The perimeter membrane is installed as a reinforcement on the entire perimeter of the roof and in the most at-risk areas, such as ridges, valleys, hips, and upstands.

The cap sheet membrane covers the entire surface and effectively seals the joints of the roof details. Its surface is granulated and resistant to wind, water and UV rays.

This system is suitable for roofs with a slope between 1:12 (8%) and 4:12 (33%).

Warranty

The RESISTO single-ply roofing system is guaranteed for 15 years against any manufacturing defect that may cause leaks. This warranty applies to low-slope roofs that use the outer perimeter instead of a drain to evacuate water. The slope of the roof must not be less than 1:12 (8%). See our warranty form available on the RESISTO website to learn more about the application conditions.

Required Tools

  • Paint roller
  • Membrane roller
  • Utility knife
  • Tape measure
  • Trowel
  • Brush

Application Conditions

The minimum installation temperature of the membranes is 50 °F (10 °C). The membranes must be applied on a clean, dry surface. It is important to condition the products at a temperature of at least 50 °F (10 °C) before installation.

Substrate

The substrate must be clean, sound and in good condition. Make sure there are no nails or screws protruding from the surface.

1
RESISTO PRIMER application

Mix the primer well before the application.

Apply a coat of RESISTO PRIMER with a brush or roller on a clean, dry surface. The RESISTO H2O PRIMER is not compatible with SEMI-RIGID ASPHALT BOARD ; therefore, we recommend using the RESISTO EXTERIOR PRIMER on this type of surface.

Allow 15 minutes to two hours for the primer to dry, depending on the ambient temperature and the amount applied. If the primer is wet, it can make the surface slippery; walk carefully on the roof.

2
Installation of the perimeter membrane ROOF UNDERLAYMENT - HIGH TEMPERATURE LASTOBOND PRO HT-N or ROOF UNDERLAYMENT - HIGH TEMPERATURE LASTOBOND PRO HT-S

Position the ROOF UNDERLAYMENT – HIGH TEMPERATURE LASTOBOND PRO HT-N or ROOF UNDERLAYMENT – HIGH TEMPERATURE LASTOBOND PRO HT-S parallel to the edge of the roof, leaving an excess of about 3 in (8 cm) on the edge where the gutter will be installed. If the gutter is already in place, install the membrane starting from the roof edge.

Install two roll widths at the bottom of the slope (near the gutter) and one for the rest of the perimeter as well as around details.

Unroll and position the roll.

While applying tension at the other end of the membrane, gradually remove the protective film.

 

Apply pressure on the membrane using a metal or hard rubber roller to obtain complete adhesion between the substrate and the membrane. This step will also prevent swelling, creases and fish mouths.

Overlap the strips laterally by approximately 3 in (8 cm).

To butt joint two pieces of membrane, an overlap of 6 in (15 cm) is required.

3
EDGE FLASHING installation

After installing the membrane, fasten the metal flashing to the edge and install a AIR AND VAPOR BARRIER MEMBRANE REDZONE strip of at least 4 in (10 cm) in width by overlapping it on the flashing and membrane already installed at the perimeter.

4
Roofing details

See the ROOF DETAILS AND WATERPROOFING guide.

 

5
GRANULATED CAP SHEET - HIGH RESISTANCE - HR CAP SHEET installation

Install the membrane horizontally, starting at the bottom of the slope. Unroll and position the roll. When the slope is rather steep (3:12 [25%] and above), it is best to mechanically fasten the membrane by adding roofing nails to the horizontal overlaps every 12 in (30 cm) before covering them with the next membrane strip (all nails must be covered with a membrane).

Remove the protective film from the GRANULATED CAP SHEET – HIGH RESISTANCE – HR CAP SHEET.

Immediately apply pressure on the membrane using a metal or hard rubber roller to obtain complete adhesion between the substrate and the membrane. This step will also prevent swelling, creases and fish mouths.

The ungranulated part of the membrane (approximately 4 in [10 cm]) should be used to ensure a good overlap between each strip; the ungranulated surface is provided for this purpose. The overlap must be positioned on the upper side of the slope.

To butt joint two strips of GRANULATED CAP SHEET – HIGH RESISTANCE – HR CAP SHEET, allow a 6 in (15 cm) overlap by first applying the RESISTO ELASTOMERIC SEALANT to cover the granulated part of the membrane to be overlapped.

6
Roofing details for GRANULATED CAP SHEET - HIGH RESISTANCE - HR CAP SHEET

LIQUID WATERPROOFING MEMBRANE RESISTOFLASHRESISTOFLASH is an excellent solution for roofing details.

SEE THE DETAILS BELOW.

 

Figure 11 and 12

 

This Installation Guide refers to the minimum installation steps required for the RESISTO product mentioned above. Please note that additional steps may be necessary depending on the substrate. However, this procedure is subject to change. RESISTO reserves the right to modify the documents and procedures at any time. Under no circumstances will RESISTO be liable for installation defects. For more information, please contact your representative, RESISTO’s technical support team, or your construction professional.

Share

Faites-vous affaire aux États-Unis?

Si oui, visitez notre site américain afin de découvrir les produits offerts au États-Unis

Do you do business in the United States?

If yes, visit our American site to discover products available there.

Faites-vous affaire aux États-Unis?

Si oui, visitez notre site américain afin de découvrir les produits offerts aux États-Unis.